The following is a description provided by Rusty Henson of the work being done to the airport at San Miguel de Allende. We have also posted the pictures sent to us by Rusty in the image gallery.

"We are placing 15 cm of compacted road base (base hidraulico) and a chip seal coat on 1100 m x 20 m. We are placing 5 m wide shoulders on both sides of compacted dirt.
We are in the process of asking the State government for 7 MM pesos to pave a total of 1500 meters x 20 meters and a large parking ramp.

Rusty"


Rick Gardner
Caribbean Sky Tours